Preliminaries | Unit | Quantity | SGD Unit Cost |
---|---|---|---|
Site protection (during construction for new premise as well as passage way from cargo lift and lift lobby). | 1 | Lumpsum | $1000.00- $2800.00 |
Supply labour, materials and tools to clean and housekeeping during fit-out period and overall cleaning before handover. | 1 | Lumpsum | $2500.00- $4000.00 |
Builder Works | Unit | Quantity | SGD Unit Cost |
---|---|---|---|
Supply labour materials and tools to replace back to existing ceiling boards and make good ceiling 'T' only affected by demolition overall before handover | 1 | Lumpsum | $2500.00- $4000.00 |
Supply labour materials and tools to construct 75mm thk partition wall c/w 40kg/m3 rockwool insulation floor to false ceiling plastered to receive finishes | 1 | sqft | $4.50 - $ 6.00 |
Supply labour tools and materials to white odourless paint for new partitions | 1 | sqft | $0.50 - $0.60 |
Supply labour materials and tools to install new roller blind.Operating System : Manual Pulley Chain | 1 | sqft | $5.00 - $7.50 |
Supply labour materials and tools to install new polypropylene range carpet tiles to offices and lift lobby area w/o skirting | 1 | sqft | $5.00 - $7.50 |
Electrical Data & Building Air Conditioning Installation Works | Unit | Quantity | SGD Unit Cost |
---|---|---|---|
Supply labour materials and tools to install 13A 2 gang s/s/o power point | 1 | unit | $85.00 - $150.00 |
Supply labour and materials to install phone cable ( CAT 5 E ) c/w faceplate | 1 | unit | $85.00 - $150.00 |
Supply labour and materials to install internet cable ( CAT 5 E ) c/w faceplate | 1 | unit | $150.00 - $250.00 |
Supply labour materials and tools to install new supply air diffuser complete with 200mm dia flexible duct. | 1 | unit | $350.00 - $450.00 |
System Furniture | Unit | Quantity | SGD Unit Cost |
---|---|---|---|
Free Standing Workstations Supply labour materials and tools to install new W1400mm x D700mm x H750mm worktop c/w modesty panel and mobile pedestal. | 1 | unit | $450.00 - $550.00 |
Supply labour materials and tools to install office chairs | 1 | unit | $180.00 - $250.00 |
- The unit price above is based on 1000sqft – 5000sqft and above in bare condition area & subject to the final design chosen.
- Measurement and prices to be confirmed on site.
- Estimate renovation cost is about $50-$ 60 (standard fit out) and could go up to $100-$150 (premium fit out) per sqft subject to the final design chosen and exclude fire sprinkler work.
- Submission to fire sprinkler work FSSD MAA, BP & FP Drawing, RI & FSSD fee – subject to unit plan compliance with SCDF regulations. The fee will be S$5000.00 to S$6000.00.
- The cost of fitting out does not incude reinstatement cost at the end of the lease term.